Hi Gurus,
We have setup a daily job run with NETCH, 2,3,1,3,2 and weekly job run with NEUPL,2,3,1,3,2
In Material Master setup-
Material type ERSA
MRP type - VB
Reorder Point =3
LOT Size = HB
MAx Stock level =5
Procuremnt type F
Pln del time =3 days
Sche MArgin Key = blank
current stock =2
In OPPQ- start in past not checked
Scenario - System is creates PR for 3 qty with NETCH, 2,3,1,3,2 but when it comes to weekly job run with NEUPL,2,3,1,3,2 , system will delete the PR and creates a Planned order for 3 qty with exception message 05 and 06..plz see screen shot
Query -
1. How to reproduced the same in Dev. client ?
2. How to stop it to create planned order, it should always creates PR?
Appreciate your response
Thanks
Sastry